Project: MattJ   -  
            Listing of Entries
    (Please mouse-over any icon to get a description of that function).



Categories
  
Builder Name:Matt Jakus   -  
Project:   The Airplane Factory - Sling TSi   -   VIEW REPORTS
Total Hours:1190.7
Start/Last Date:Dec 01, 2019 - Jan 29, 2023
Engine:Rotax 915is
Panel:Garmin 3X
 
Friendly URL: https://eaabuilderslog.org?s=MattJ

Home or Last Project Picture

Jul 28, 2020     SB # 18 Insufficient swaging of oval sleeves on the rudder cables - (4.5 hours)       Category: Controls
7/31/2020

Completed the SB#18. This is a 2 part process: first, inspect the crimp width of less than 8.9 mm and then to put corrosion resistant grease on the fittings. It was not required to re-wrap the ends but I did anyway.


7/28/2020

Received a SB for inspection of the Rudder cables crimps. So a read over and inspection will push aside the next few days plans. I will need to order some materials to comply.

At least I get some of the SB's during the build so it is relatively easy to take care of them. The numbering system is a little odd even though it is SB#18 it does not mean there are 18 SBs for this particular model.


 


NOTE: This information is strictly used for the EAA Builders Log project within the EAA organization.     -     Policy     -     © Copyright 2024 Brevard Web Pro, Inc.